2010年PMP美國項目管理考試習題及答案六十九
QUEST Which of the following statements about the cost of quality are true?
A the cost of quality is the expense of nonconformance to requirements and specifications.
B the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.
C quality control programs should be implemented when the cost of quality are deemed affordable by management.
D A and B.
E A and C
參考答案:A
QUEST Japanese quality control has improved dramatically in the last 30 years for all of the following reasons except:
A the use of quality circles.
B small, continuous improvements in quality control.
C the use of worker suggestion systems.
D the use of quality control charts.
E focusing quality control efforts on production outputs.
參考答案:E
QUEST Control chart theory is based on the differentiation of the causes of variations in quality. Variations may be produced by assignable causes. All of the following are examples of assignable causes except:
A differences among machines.
B differences among workers.
C differences among materials.
D differences in each of these factors over time.
E None of the above (all are examples)
參考答案:E
QUEST The rule of seven used by quality control engineers states that if a run of seven or more samples lays on one side of the process mean, then the process is out of control. What is the probability that this condition is the result of random variations.
A 14.30%
B 3.12%
C 2.73%
D 1.56%
E 0.78%
參考答案:D
QUEST Two sources of variation in the length of hex bolts exist. Production variation and measurement error. The QC manager knows that the standard deviation from these sources is 0.24" and 0.43" , respectively. What is the total standard deviation.
A .10 inch.
B .19 inch.
C .34 inch.
D .49 inch.
E .67 inch.
參考答案:D
相關試題:
2010年PMP美國項目管理考試習題及答案六十八
試題推薦:
2010年PMP美國項目管理認定考試全真模擬試題精選1
2010年PMP美國項目管理認定考試全真模擬試題精選2
2010年PMP美國項目管理認定考試全真模擬試題精選3
- 12003年工程建設合同管理考試試卷
- 2項目管理與招標采購第二章:業(yè)主與項目管理咨詢單位
- 3造價工程師案例分析復習資料——工程計量與計價
- 4地基設計有哪些原則?
- 5園林景觀工程構成及其成本分析
- 62015年咨詢工程師《項目決策分析與評價》練習題(10)
- 7地下水對鋼筋混凝土的結晶分解復合類腐蝕
- 82015年監(jiān)理工程師考試備考中做題需注意
- 9擬定對目標控制有利的建設工程組織管理模式
- 10造價工程師復習資料:申請領取施工許可證應具備的條件
- 11造價工程師技術與計量(土建)復習資料——軟化性
- 122015年招標師考試應試技巧和答題注意事項
- 13邯鄲市2015年度注冊安全工程師考試報名時間為4月22日至5月13日
- 14注冊監(jiān)理工程師考試考場應試技巧介紹
- 15中國某建設總公司塔式起重機安裝與驗收施工工藝
- 16造價工程師案例分析復習要點:質保金扣除
- 17景觀工程施工方案
- 182013年二級建造師《法規(guī)及相關知識》每日一練(12.4)
- 19溶劑型氯丁橡膠瀝青防水涂料施工工藝506
- 20安全工程師考試《法律法規(guī)》習題班第八講講義(11)
- 21三峽大壩旅游景點從9月25日免費開放給中國游客
- 22某地區(qū)地下管道工程施工方案 14p
- 23選擇遼寧二級建造師培訓機構時的注意事項
- 24[天津市]06年安全工程師補報名通知
- 2518號工字鋼懸挑腳手架穩(wěn)定性計算一例
- 26網(wǎng)絡圖繪制方法簡介
- 272015年安全工程師相關法規(guī)模擬練習(7)
- 282015年安全工程師《安全生產(chǎn)法》:安全生產(chǎn)標準體系
- 29現(xiàn)金管理紀律 內(nèi)容
- 302015年招標師《項目管理》章節(jié)考點:工程項目監(jiān)理制度
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓